The project involved the furnishing of an office area and meant manufacturing and installing 120 m2 glass partitions and 17 glass doors. For installation, we used a Dorma fixed glazing frame system and Dorma Universal hardware, both with the same finish: anodized aluminium. The glass panels are 10mm thick and were covered with a patterned sandblasting-like film, made with a cutter plotter.

Project time span: 15 days.